               the complete construction of the home described in the                 
               plans attached hereto and to be built on Lot #30 Perder                
               Lane, South River Colony, Anne Arundel County, Mary-                   
               land.  The lot is not part of this contract.                           
                  *       *       *       *       *       *       *                   
               ARTICLE FOUR -- CONTRACT SUM                                           
               The Owner [petitioner and Ms. Davis] shall pay to MONA                 
               BUILDERS & DEVELOPERS, INC. for the performance of the                 
               work, subject to additions and deductions by change                    
               order as provided in the General Conditions, in current                
               funds, the sum of $935,000.00 (Nine Hundred Thirty Five                
               Thousand Dollars).                                                     
               ARTICLE FIVE -- PAYMENT                                                
               The Contract sum will be paid as follows:                              

               1.   Upon ratification of Contract.        $ 15,000.00                 
               2.   Upon installation of foundation, 1st   159,240.00                 
                    floor joists and decking installed.                               
               3.   Upon installation of exterior walls,   184,000.00                 
                    roof sheathed and interior partitions                             
                    framed.                                                           
               4.   Upon rough-ins of plumbing, mechani-   230,000.00                 
                    cal and electric, roof shingles in-                               
                    stalled and installation of windows                               
                    and doors.                                                        
               5.   Upon drywall being finished, exterior  230,000.00                 
                    walls completed, and house trimmed                                
                    out.                                                              
               6.   Upon plumbing, electrical, mechanical  116,760.00                 
                    fixtures installed; kitchen cabinets                              
                    installed; flooring installed; paint-                             
                    ing completed and approval by Anne                                
                    Arundel County inspector.                                         
                                                 TOTAL   $ 935,000.00                 
               MONA BUILDERS & DEVELOPERS, INC. will adhere to the                    
               lending institution’s draw schedule; MONA BUILDERS &                   
               DEVELOPERS, INC. will be a named party on each draw                    