-4- check. The above is our standard draw schedule. We would prefer 8 to 10 draw payments due to the amount of the contract. ARTICLE SIX -- CHANGE ORDERS 1) Every custom home has a few change orders. As the project evolves, you will probably want to make some changes. That’s one of the great opportuni- ties you have by custom building. The Project Manager is available to discuss any changes you consider. On average, change orders amount to 4- 9% of the Proposal Price. We suggest you plan accordingly. * * * * * * * 6) Please note, a fee of 15% for overhead and profit will be added to the actual and/or estimated cost for all change orders. The fee is waived for change orders that result in a credit. [Handwrit- ten addition.] Upon substantial completion of the Contract, all amounts due to Owner as a credit shall be increased by 10% for reimbursement to Owner of overhead and profit previously included in the contract sum. * * * * * * * ARTICLE ELEVEN -- MONA BUILDERS & DEVELOPERS, INC. 11.1 MONA BUILDERS & DEVELOPERS, INC. shall supervise and direct the Work, using best skill and attention. MONA BUILDERS & DEVELOPERS, INC., shall be solely responsible for all construction means, methods, tech- niques, sequences and procedures for coordinating all portions of the Work under the Contract. * * * * * * * 11.3 MONA BUILDERS & DEVELOPERS, INC. shall at all times enforce strict discipline and good order among employees, and shall not employ on the Work any unfit person or anyone not skilled in the task assigned to him. * * * * * * *Page: Previous 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Next
Last modified: May 25, 2011