            Subsection 3.8 states:                                                                      
                        3.8  Payment for Costs of Construction, Costs of                                
                  Plant and Other Costs.  Payment by the Co-owners of                                   
                  their share of Costs of Construction and Other Costs                                  
                  * * * shall be made based upon the statements prepared                                
                  and submitted to the Co-owners by the Project                                         
                  Management Committee * * *                                                            
            Subsection 3.12 states:                                                                     
                        3.12 Completion of Construction.  The Co-owners                                 
                  agree, consistent with their respective                                               
                  responsibilities and obligations and the other terms                                  
                  set forth in this Agreement, to complete the                                          
                  construction of the Joint Facilities in accordance with                               
                  the schedule established pursuant to Section 5.4.2.                                   
                  Section 5 of the joint agreement is entitled “Coordination                            
            and Administration”.  Subsection 5.4.2 states:                                              
                        5.4.2 Completion Of Construction.  The Date of                                  
                  Commercial Operation for Coal Unit 1 shall be December                                
                  31, 1986, and for Coal Unit 2 shall be June 30, 1988,                                 
                  unless such Dates of Commercial Operation are changed                                 
                  pursuant to this Section 5.4.2.  The Project Management                               
                  Committee shall perform its responsibilities hereunder                                
                  to effect the completion of the construction of the                                   
                  Joint Facilities in accordance with such schedule.                                    
                  * * *                                                                                 
            The project management committee is comprised of one                                        
            representative and one alternate from each of the coowners.                                 
            Subsection 5.4.1 describes the responsibilities of the project                              
            management committee with respect to the construction of the                                
            SJRPP.                                                                                      
                  Section 9 of the agreement is entitled “Liabilities”.                                 
            Subsection 9.1 states, in pertinent part:                                                   
                  any liability or payment, cost, expense or obligation                                 
                  arising from a claim of liability to a third party or                                 





Page:  Previous  139  140  141  142  143  144  145  146  147  148  149  150  151  152  153  154  155  156  157  158  Next