FPL Group, Inc. & Subsidiaries - Page 93

                                               - 175 -                                                  
                  Also, the expenditure requisitions that relate to the                                 
            transmission line components refer to budget items.  With the                               
            exception of the budget item for the Hiatus-Melaleuca 230-kV                                
            line,125 each budget item states that petitioner planned to begin                           
            construction after December 31, 1985.126  We find that petitioner                           

                  124(...continued)                                                                     
            Third feeder-                       1988                  ER 4512                           
            Turnpike Substation                                                                         
            Third 230-kV line-           Late 1988/early 1989         ER 5056                           
            Turnpike substation                                                                         
            230-kV line-                      Late 1986               ER 1333                           
            Andytown-Trace                                                                              
            Lauderdale #4 terminal-             1987                  ER 1645                           
            Andytown substation                                                                         
            230-kV line-Andytown                1987                  ER 1676                           
            230-kV line-Hiatus-                 1986                  ER 1332                           
            Melaleuca                                                                                   

                  125 ER 1332, which authorizes expenditures for the Hiatus-                            
            Melaleuca 230-kV line, refers to BI 254.  BI 254 states that the                            
            “Date work to be started” is November 1985.                                                 
                  126 ER 5366, which authorizes expenditures for the Crane-                             
            Turnpike 230-kV line, refers to BI 206.  BI 206 states that the                             
            “Date work to be started” is September 1989.                                                
                  ER 1333, which authorizes expenditures to construct the 230-                          
            kV Andytown-Trace line, refers to BI 246.  ER 1645, which                                   
            authorizes expenditures to construct the Lauderdale #4 terminal                             
            at the Andytown substation, also refers to BI 246.  ER 1676,                                
            which authorizes expenditures to install relay equipment for the                            
            230-kV line at Andytown, refers to BI 246.  BI 246 states that                              
            the “Date work to be started” is July 1987.                                                 
                  BI 634, relating to the third-feeder position and the third                           
            230-kV line at the Turnpike substation, was not offered into                                
            evidence.  “[T]he failure of a party to introduce evidence within                           
            his possession and which, if true, would be favorable to him,                               
                                                                          (continued...)                




Page:  Previous  165  166  167  168  169  170  171  172  173  174  175  176  177  178  179  180  181  182  183  184  Next

Last modified: May 25, 2011