- 175 -
Also, the expenditure requisitions that relate to the
transmission line components refer to budget items. With the
exception of the budget item for the Hiatus-Melaleuca 230-kV
line,125 each budget item states that petitioner planned to begin
construction after December 31, 1985.126 We find that petitioner
124(...continued)
Third feeder- 1988 ER 4512
Turnpike Substation
Third 230-kV line- Late 1988/early 1989 ER 5056
Turnpike substation
230-kV line- Late 1986 ER 1333
Andytown-Trace
Lauderdale #4 terminal- 1987 ER 1645
Andytown substation
230-kV line-Andytown 1987 ER 1676
230-kV line-Hiatus- 1986 ER 1332
Melaleuca
125 ER 1332, which authorizes expenditures for the Hiatus-
Melaleuca 230-kV line, refers to BI 254. BI 254 states that the
“Date work to be started” is November 1985.
126 ER 5366, which authorizes expenditures for the Crane-
Turnpike 230-kV line, refers to BI 206. BI 206 states that the
“Date work to be started” is September 1989.
ER 1333, which authorizes expenditures to construct the 230-
kV Andytown-Trace line, refers to BI 246. ER 1645, which
authorizes expenditures to construct the Lauderdale #4 terminal
at the Andytown substation, also refers to BI 246. ER 1676,
which authorizes expenditures to install relay equipment for the
230-kV line at Andytown, refers to BI 246. BI 246 states that
the “Date work to be started” is July 1987.
BI 634, relating to the third-feeder position and the third
230-kV line at the Turnpike substation, was not offered into
evidence. “[T]he failure of a party to introduce evidence within
his possession and which, if true, would be favorable to him,
(continued...)