Sec. 2269.309. SUBMISSION OF DESIGN AFTER SELECTION. After selection of the design-build firm, that firm's architects or engineers shall submit all design elements for review and determination of scope compliance to the governmental entity or the governmental entity's architect or engineer before or concurrently with construction.
Added by Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628), Sec. 2.08, eff. September 1, 2011.
Redesignated from Government Code, Chapter 2267 by Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.001(23), eff. September 1, 2013.
Section: Previous 2269.302 2269.303 2269.304 2269.305 2269.306 2269.307 2269.308 2269.309 2269.310 2269.311 2269.351 2269.352 2269.353 2269.354 2269.355 NextLast modified: September 28, 2016