Texas Government Code § 2269.361 Procedures For Combination Of Technical And Cost Proposals

Sec. 2269.361. PROCEDURES FOR COMBINATION OF TECHNICAL AND COST PROPOSALS. (a) A governmental entity shall request proposals from design-build firms identified under Section 2269.359(c). A firm must submit a proposal not later than the 180th day after the date the governmental entity makes a public request for the proposals from the selected firms. The request for proposals must include:

(1) a design criteria package;

(2) if the project site is identified, a geotechnical baseline report or other information that provides the design-build firm minimum geotechnical design parameters to submit a proposal;

(3) detailed instructions for preparing the technical proposal and the items to be included, including a description of the form and level of completeness of drawings expected; and

(4) the relative weighting of the technical and price proposals and the formula by which the proposals will be evaluated and ranked.

(b) The technical proposal is a component of the proposal under this section.

(c) Each proposal must include a sealed technical proposal and a separate sealed cost proposal.

(d) The technical proposal must address:

(1) project approach;

(2) anticipated problems;

(3) proposed solutions to anticipated problems;

(4) ability to meet schedules;

(5) conceptual engineering design; and

(6) other information requested by the governmental entity.

(e) The governmental entity shall first open, evaluate, and score each responsive technical proposal submitted on the basis of the criteria described in the request for proposals and assign points on the basis of the weighting specified in the request for proposals. The governmental entity may reject as nonresponsive any firm that makes a significant change to the composition of its firm as initially submitted. The governmental entity shall subsequently open, evaluate, and score the cost proposals from firms that submitted a responsive technical proposal and assign points on the basis of the weighting specified in the request for proposals. The governmental entity shall select the design-build firm in accordance with the formula provided in the request for proposals.

Added by Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628), Sec. 2.08, eff. September 1, 2011.

Redesignated from Government Code, Chapter 2267 by Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.001(23), eff. September 1, 2013.

Amended by:

Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.002(16), eff. September 1, 2013.

Section: Previous  2269.354  2269.355  2269.356  2269.357  2269.358  2269.359  2269.360  2269.361  2269.3615  2269.362  2269.363  2269.364  2269.365  2269.366  2269.367  Next