Sec. 121.453. PERMIT APPLICATION. (a) A person may not begin construction of a sour gas pipeline facility before the person obtains from the railroad commission a permit to construct the facility.
(b) An applicant for a permit to construct a sour gas pipeline facility must:
(1) publish notice of the application in a form determined by the railroad commission in a newspaper of general circulation in each county that contains part of the proposed route of the sour gas pipeline facility; and
(2) provide a copy of the application to the county clerk of each county that contains part of the proposed route.
Added by Acts 1999, 76th Leg., ch. 62, Sec. 18.13(a), eff. Sept. 1, 1999.
Section: Previous 121.309 121.310 121.401 121.402 121.403 121.451 121.452 121.453 121.454 121.5005 121.501 121.502 121.503 121.504 121.505 NextLast modified: September 28, 2016