Sec. 36.006. BURDEN OF PROOF. In a proceeding involving a proposed rate change, the electric utility has the burden of proving that:
(1) the rate change is just and reasonable, if the utility proposes the change; or
(2) an existing rate is just and reasonable, if the proposal is to reduce the rate.
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.