Texas Utilities Code § 36.006 Burden Of Proof

Sec. 36.006. BURDEN OF PROOF. In a proceeding involving a proposed rate change, the electric utility has the burden of proving that:

(1) the rate change is just and reasonable, if the utility proposes the change; or

(2) an existing rate is just and reasonable, if the proposal is to reduce the rate.

Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.

Section: Previous  36.001  36.002  36.003  36.004  36.005  36.006  36.007  36.008  36.009  36.051  36.052  36.053  36.054  36.055  36.056  Next