Texas Utilities Code § 36.053 Components Of Invested Capital

Sec. 36.053. COMPONENTS OF INVESTED CAPITAL. (a) Electric utility rates shall be based on the original cost, less depreciation, of property used by and useful to the utility in providing service.

(b) The original cost of property shall be determined at the time the property is dedicated to public use, whether by the utility that is the present owner or by a predecessor.

(c) In this section, the term "original cost" means the actual money cost or the actual money value of consideration paid other than money.

(d) If the commission issues a certificate of convenience and necessity or, acting under Section 39.203(e), orders an electric utility or a transmission and distribution utility to construct or enlarge transmission or transmission-related facilities to facilitate meeting the goal for generating capacity from renewable energy technologies under Section 39.904(a), the commission shall find that the facilities are used and useful to the utility in providing service for purposes of this section and are prudent and includable in the rate base, regardless of the extent of the utility's actual use of the facilities.

Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.

Amended by:

Acts 2005, 79th Leg., 1st C.S., Ch. 1 (S.B. 20), Sec. 1, eff. September 1, 2005.

Section: Previous  36.005  36.006  36.007  36.008  36.009  36.051  36.052  36.053  36.054  36.055  36.056  36.057  36.058  36.059  36.060  Next

Last modified: September 28, 2016