Texas Utilities Code § 37.058 Certificate And Determination Issued To Certain Non-ercot Utilities For Generating Facility

Sec. 37.058. CERTIFICATE AND DETERMINATION ISSUED TO CERTAIN NON-ERCOT UTILITIES FOR GENERATING FACILITY. (a) This section applies only to an electric utility that operates solely outside of ERCOT.

(b) An electric utility may file with the commission a request that the commission:

(1) grant a certificate for an electric generating facility;

(2) make a public interest determination for the purchase of an existing electric generating facility under Section 14.101; or

(3) both grant a certificate and make a determination.

(c) Notwithstanding any other law, in a proceeding involving the purchase of an existing electric generating facility, the commission shall issue a final order on a certificate for the facility or making a determination on the facility required by Section 14.101, as applicable, not later than the 181st day after the date a request for the certificate or determination is filed with the commission under Subsection (b). For generating facilities granted a certificate under this subsection, notwithstanding Section 36.053, the utility's recoverable invested capital included in rates shall be determined by the commission.

(d) Notwithstanding any other law, in a proceeding involving a newly constructed generating facility, the commission shall issue a final order on a certificate for the facility not later than the 366th day after the date a request for the certificate is filed with the commission under Subsection (b).

Added by Acts 2015, 84th Leg., R.S., Ch. 733 (H.B. 1535), Sec. 4, eff. June 17, 2015.

Section: Previous  37.0521  37.053  37.054  37.0541  37.055  37.056  37.057  37.058  37.059  37.060  37.061  37.101  37.102  37.151  37.152  Next

Last modified: September 28, 2016