Sec. 37.0541. CONSOLIDATION OF CERTAIN PROCEEDINGS. The commission shall consolidate the proceeding on an application to obtain or amend a certificate of convenience and necessity for the construction of a transmission line with the proceeding on another application to obtain or amend a certificate of convenience and necessity for the construction of a transmission line if it is apparent from the applications or a motion to intervene in either proceeding that the transmission lines that are the subject of the separate proceedings share a common point of interconnection. This section does not apply to a proceeding on an application for a certificate of convenience and necessity for a transmission line to serve a competitive renewable energy zone as part of a plan developed by the commission under Section 39.904(g)(2).
Added by Acts 2009, 81st Leg., R.S., Ch. 1170 (H.B. 3309), Sec. 1, eff. June 19, 2009.
Section: Previous 37.001 37.051 37.052 37.0521 37.053 37.054 37.0541 37.055 37.056 37.057 37.058 37.059 37.060 37.061 37.101 NextLast modified: September 28, 2016