(a)
(1) procedures associated with maintaining and installing continuous welded rail and its attendant structure, including cold weather installation procedures;
(2) the need for revisions to regulations on track excepted from track safety standards; and
(3) employee safety.
(b)
(c)
(d)
(1) inspection procedures to identify internal rail defects, before they reach imminent failure size, in rail that has significant shelling; and
(2) any specific actions that should be taken when a rail surface condition, such as shelling, prevents the identification of internal defects.
(e)
(1)
(A) require each track owner using continuous welded rail track to include procedures (in its procedures filed with the Administration pursuant to section 213.119 of title 49, Code of Federal Regulations) to improve the identification of cracks in rail joint bars;
(B) instruct Administration track inspectors to obtain copies of the most recent continuous welded rail programs of each railroad within the inspectors' areas of responsibility and require that inspectors use those programs when conducting track inspections; and
(C) establish a program to review continuous welded rail joint bar inspection data from railroads and Administration track inspectors periodically.
(2)
(Pub. L. 103–272, §1(e), July 5, 1994, 108 Stat. 879; Pub. L. 103–440, title II, §208, Nov. 2, 1994, 108 Stat. 4621; Pub. L. 109–59, title IX, §9005(a), Aug. 10, 2005, 119 Stat. 1924.)
Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
---|---|---|
20142(a) | 45:431(s)(1) (1st sentence), (2). | Oct. 16, 1970, Pub. L. 91–458, 84 Stat. 971, §202(s); added Sept. 3, 1992, Pub. L. 102–365, §8, 106 Stat. 976. |
20142(b) | 45:431(s)(1) (last sentence). | |