The FPA empowers FERC to issue licenses for projects "necessary or convenient . . . for the development, transmission, and utilization of power across, along, from, or in any of the streams . . . over which Congress has jurisdiction." § 797(e). The FPA also requires FERC to consider a project's effect on fish and wildlife. §§ 797(e), 803(a)(1). In California v. FERC, supra, we held that the California Water Resources Control Board, acting pursuant to state law, could not impose a minimum stream flow which conflicted with minimum stream flows contained in a FERC license. We concluded that the FPA did not "save" to the States this authority. Id., at 498.

No such conflict with any FERC licensing activity is presented here. FERC has not yet acted on petitioners' license application, and it is possible that FERC will eventually deny petitioners' application altogether. Alternatively, it is quite possible, given that FERC is required to give equal consideration to the protection of fish habitat when deciding whether to issue a license, that any FERC license would contain the same conditions as the state § 401 certification. Indeed, at oral argument the Deputy Solicitor General stated that both EPA and FERC were represented in this proceeding, and that the Government has no objection to the stream flow condition contained in the § 401 certification. Tr. of Oral Arg. 43-44.

Finally, the requirement for a state certification applies not only to applications for licenses from FERC, but to all federal licenses and permits for activities which may result in a discharge into the Nation's navigable waters. For example, a permit from the Army Corps of Engineers is required for the installation of any structure in the navigable waters which may interfere with navigation, including piers, docks, and ramps. Rivers and Harbors Appropriation Act of 1899, 30 Stat. 1151, § 10, 33 U. S. C. § 403. Similarly, a permit must be obtained from the Army Corps of Engineers