Cite as: 535 U. S. 302 (2002)

Opinion of the Court

In rejecting petitioners' per se rule, we do not hold that the temporary nature of a land-use restriction precludes finding that it effects a taking; we simply recognize that it should not be given exclusive significance one way or the other.

A narrower rule that excluded the normal delays associated with processing permits, or that covered only delays of more than a year, would certainly have a less severe impact on prevailing practices, but it would still impose serious financial constraints on the planning process.31 Unlike the "extraordinary circumstance" in which the government deprives a property owner of all economic use, Lucas, 505 U. S., at 1017, moratoria like Ordinance 81-5 and Resolution 83- 21 are used widely among land-use planners to preserve the status quo while formulating a more permanent development strategy.32 In fact, the consensus in the planning com-31 Petitioners fail to offer a persuasive explanation for why moratoria should be treated differently from ordinary permit delays. They contend that a permit applicant need only comply with certain specific requirements in order to receive one and can expect to develop at the end of the process, whereas there is nothing the landowner subject to a moratorium can do but wait, with no guarantee that a permit will be granted at the end of the process. Brief for Petitioners 28. Setting aside the obvious problem with basing the distinction on a course of events we can only know after the fact—in the context of a facial challenge—petitioners' argument breaks down under closer examination because there is no guarantee that a permit will be granted, or that a decision will be made within a year. See, e. g., Dufau v. United States, 22 Cl. Ct. 156 (1990) (holding that 16-month delay in granting a permit did not constitute a temporary taking). Moreover, under petitioners' modified categorical rule, there would be no per se taking if TRPA simply delayed action on all permits pending a regional plan. Fairness and justice do not require that TRPA be penalized for achieving the same result, but with full disclosure.

32 See, e. g., Santa Fe Village Venture v. Albuquerque, 914 F. Supp. 478, 483 (N. M. 1995) (30-month moratorium on development of lands within the Petroglyph National Monument was not a taking); Williams v. Central, 907 P. 2d 701, 703-706 (Colo. App. 1995) (10-month moratorium on development in gaming district while studying city's ability to absorb growth was not a compensable taking); Woodbury Place Partners v. Woodbury, 492 N. W. 2d 258 (Minn. App. 1993) (moratorium pending review

337

Page:   Index   Previous  29  30  31  32  33  34  35  36  37  38  39  40  41  42  43  Next

Last modified: October 4, 2007