Revised Code of Washington - RCW Title 60 Liens - Section 60.24.150 Enforcement against all or part of property

§ 60.24.150. Enforcement against all or part of property

Any person who shall bring a civil action to enforce the lien herein provided for, or any person having a lien as herein provided for, who shall be made a party to any such civil action, has the right to demand that such lien be enforced against the whole or any part of the saw logs, spars, piles or other timber or manufactured lumber or shingles upon which he has performed labor or which he has assisted in securing or obtaining, or which he has cut on his timber land during the eight months next preceding the filing of his lien, for all his labor upon or for all his assistance in obtaining or securing said logs, spars, piles or other timber, or in manufacturing said lumber or shingles during the whole or any part of the eight months mentioned in *section seven (7) of this act, or for timber cut during the whole or any part of the eight months above mentioned. And where proceedings are commenced against any lot of saw logs, spars, piles or other timber or lumber or shingles as herein provided, and some of the lienors claim liens against the specific logs, spars, piles or other timber or lumber or shingles proceeded against, and others against the same generally, to secure their claims for work and labor, the priority of the liens shall be determined as hereinbefore provided.

[1893 c 132 § 14; RRS § 1175. Prior: Code 1881 § 1952; 1877 p 218 § 14.]

Notes:
     *Reviser's note: "section seven (7) of this act" is codified as RCW 60.24.075. Section 5 (codified as RCW 60.24.040) was probably intended.

Sections:  Previous  60.24.070  60.24.075  60.24.080  60.24.100  60.24.110  60.24.120  60.24.130  60.24.140  60.24.150  60.24.160  60.24.170  60.24.180  60.24.190  60.24.195  60.24.200  Next

Last modified: April 7, 2009