§ 74.46.050. Improperly completed or late cost report -- Fines -- Adverse rate actions -- Rules
(1) If the cost report is not properly completed or if it is not received by the due date, all or part of any payments due under the contract may be withheld by the department until such time as the required cost report is properly completed and received.
(2) The department may impose civil fines, or take adverse rate action against contractors and former contractors who do not submit properly completed cost reports by the applicable due date. The department is authorized to adopt rules addressing fines and adverse rate actions including procedures, conditions, and the magnitude and frequency of fines.
[1998 c 322 § 4; 1985 c 361 § 5; 1980 c 177 § 5.]
Notes:
Savings -- 1985 c 361: See note following RCW 74.46.020.
Sections: Previous 74.46.010 74.46.020 74.46.030 74.46.040 74.46.050 74.46.060 74.46.080 74.46.090 74.46.100 74.46.155 74.46.165 74.46.190 74.46.200 74.46.220 74.46.230 Next
Last modified: April 7, 2009