Revised Code of Washington - RCW Title 39 Public Contracts And Indebtedness - Section 39.12.050 False statement or failure to file -- Penalty -- Unpaid wages lien against bond and retainage -- Prohibitions on bidding on future contracts -- Hearing

§ 39.12.050. False statement or failure to file -- Penalty -- Unpaid wages lien against bond and retainage -- Prohibitions on bidding on future contracts -- Hearing

(1) Any contractor or subcontractor who files a false statement or fails to file any statement or record required to be filed under this chapter and the rules adopted under this chapter, shall, after a determination to that effect has been issued by the director after hearing under chapter 34.05 RCW, forfeit as a civil penalty the sum of five hundred dollars for each false filing or failure to file, and shall not be permitted to bid, or have a bid considered, on any public works contract until the penalty has been paid in full to the director. The civil penalty under this subsection shall not apply to a violation determined by the director to be an inadvertent filing or reporting error. Civil penalties shall be deposited in the public works administration account.

To the extent that a contractor or subcontractor has not paid wages at the rate due pursuant to RCW 39.12.020, and a finding to that effect has been made as provided by this subsection, such unpaid wages shall constitute a lien against the bonds and retainage as provided in RCW 18.27.040, 19.28.041, 39.08.010, and 60.28.010.

(2) If a contractor or subcontractor is found to have violated the provisions of subsection (1) of this section for a second time within a five year period, the contractor or subcontractor shall be subject to the sanctions prescribed in subsection (1) of this section and shall not be allowed to bid on any public works contract for one year. The one year period shall run from the date of notice by the director of the determination of noncompliance. When an appeal is taken from the director's determination, the one year period shall commence from the date of the final determination of the appeal.

The director shall issue his or her findings that a contractor or subcontractor has violated the provisions of this subsection after a hearing held subject to the provisions of chapter 34.05 RCW.

[2001 c 219 § 1; 1985 c 15 § 3; 1977 ex.s. c 71 § 1; 1973 c 120 § 1; 1945 c 63 § 5; Rem. Supp. 1945 § 10322-24.]

Notes:
     Severability -- 1985 c 15: See note following RCW 39.12.065.

Sections:  Previous  39.12.015  39.12.020  39.12.021  39.12.022  39.12.026  39.12.030  39.12.040  39.12.042  39.12.050  39.12.055  39.12.060  39.12.065  39.12.070  39.12.080  39.12.900  Next

Last modified: April 7, 2009