§ 39.12.055. Prohibitions on bidding on future contracts
A contractor shall not be allowed to bid on any public works contract for one year from the date of a final determination that the contractor has committed any combination of two of the following violations or infractions within a five-year period:
(1) Violated RCW 51.48.020(1) or 51.48.103; or
(2) Committed an infraction or violation under chapter 18.27 RCW for performing work as an unregistered contractor.
[2008 c 120 § 3.]
Notes:
Conflict with federal requirements -- Severability -- 2008 c 120: See notes following RCW 18.27.030.