§ 47.28.035. Cost of project, defined
The cost of any project for the purposes of RCW 47.28.030 shall be the aggregate of all amounts to be paid for labor, material, and equipment on one continuous or interrelated project where work is to be performed simultaneously. The department shall not permit the construction of any project by state forces by dividing a project into units of work or classes of work to give the appearance of compliance with RCW 47.28.030.
[1984 c 194 § 2.]