(1)(a) Except as provided in paragraph (d) of this subsection, the specifications for every contract for public works shall contain a provision stating the existing state prevailing rate of wage and, if applicable, the federal prevailing rate of wage required under the Davis-Bacon Act (40 U.S.C. 3141 et seq.) that may be paid to workers in each trade or occupation required for the public works employed in the performance of the contract either by the contractor or subcontractor or other person doing or contracting to do the whole or any part of the work contemplated by the contract. When the prevailing rates of wage are available electronically or are accessible on the Internet, the rates may be incorporated into the specifications by referring to the electronically accessible or Internet-accessible rates and by providing adequate information about how to access the rates.
(b) If a public agency is required under paragraph (a) of this subsection to include the state and federal prevailing rates of wage in the specifications, the public agency also shall include in the specifications information showing which prevailing rate of wage is higher for workers in each trade or occupation in each locality, as determined by the Commissioner of the Bureau of Labor and Industries under ORS 279C.815 (2)(c).
(c) Every contract and subcontract shall contain a provision that the workers shall be paid not less than the specified minimum hourly rate of wage in accordance with ORS 279C.838 and 279C.840.
(d) A public works project described in ORS 279C.800 (6)(a)(B) or (C) is subject to the existing state prevailing rate of wage or, if applicable, the federal prevailing rate of wage required under the Davis-Bacon Act that is in effect at the time a public agency enters into an agreement with a private entity for the project. After that time, the specifications for any contract for the public works shall include the applicable prevailing rate of wage.
(2) The specifications for every contract for public works between a public agency and a contractor shall contain a provision stating that a fee is required to be paid to the Commissioner of the Bureau of Labor and Industries as provided in ORS 279C.825 (1). The contract shall contain a provision that the fee shall be paid to the commissioner under the administrative rule of the commissioner.
(3) The specifications for every contract for public works shall contain a provision stating that the contractor and every subcontractor must have a public works bond filed with the Construction Contractors Board before starting work on the project, unless exempt under ORS 279C.836 (4), (7), (8) or (9). Every contract awarded by a contracting agency shall contain a provision requiring the contractor:
(a) To have a public works bond filed with the Construction Contractors Board before starting work on the project, unless exempt under ORS 279C.836 (4), (7), (8) or (9).
(b) To include in every subcontract a provision requiring the subcontractor to have a public works bond filed with the Construction Contractors Board before starting work on the project, unless exempt under ORS 279C.836 (4), (7), (8) or (9). [2003 c.794 §168; 2005 c.360 §10; 2007 c.415 §2; 2007 c.764 §37; 2007 c.844 §4]
Section: Previous 279C.808 279C.810 279C.815 279C.817 279C.820 279C.825 279C.827 279C.830 279C.835 279C.836 279C.838 279C.840 279C.845 279C.850 279C.855 NextLast modified: August 7, 2008