Oregon Statutes - Chapter 523 - Geothermal Heating Districts - Section 523.110 - Regulations on use of geothermal heat; effect of failure to comply.

Any district may adopt and promulgate regulations concerning the use of geothermal heat and the property of the district. The board of commissioners may refuse to supply any building, place or premises with geothermal heat where the user fails after 10 days’ written notice to comply with the regulations. The written notice shall be by registered mail or by certified mail with return receipt and shall be deemed given when it is deposited in the United States Post Office properly addressed with postage prepaid. [1975 c.782 §11; 1991 c.249 §40]

Section:  Previous  523.015  523.020  523.030  523.040  523.050  523.060  523.070  523.110  523.120  523.130  523.140  523.150  523.160  523.210  523.220  Next

Last modified: August 7, 2008