Vandra Bros. Construction Co., Inc. - Page 3




                                        - 3 -                                         
          instead relying on suppliers to deliver needed materials to the             
          construction site at the appropriate time.  Petitioner only                 
          ordered the materials it needed for the job for the particular              
          day.  Petitioner had no plant or other facility to store                    
          materials and could not store materials at the construction site.           
          (Petitioner left no material on site overnight except,                      
          occasionally, a negligible amount.)  Concrete could not be stored           
          on site for an additional reason:  Within a few hours of                    
          delivery, it would harden and become useless and worthless.                 
          Thus, petitioner tried to estimate as closely as possible the               
          amount of materials needed so there would not be anything left              
          over.  Petitioner bore the cost of any wasted materials if they             
          were the result of an over order, or, in the case of concrete, of           
          it not being laid in time.  If the materials were defective or,             
          in the case of concrete, delivered too late, the supplier was               
          responsible and bore the cost.                                              
               Virtually all of petitioner’s projects required laying some            
          concrete.  Petitioner also engaged in related work, such as                 
          preparing a site by removing existing concrete or stone.                    
          Petitioner also installed items such as reinforcing steel, piping           
          for sewers and drainage, and guardrails.  During the year in                
          issue, 67 percent of petitioner’s total materials cost was due to           
          concrete, 16 percent was due to stone, 6 percent was due to                 
          reinforcing material, and the remainder was due to other                    






Page:  Previous  1  2  3  4  5  6  7  8  9  10  11  12  Next

Last modified: May 25, 2011