Vandra Bros. Construction Co., Inc. - Page 7




                                        - 7 -                                         
          the engineer inspected the concrete to make sure it was not                 
          defective and had the right to reject it if it was.  If concrete            
          was rejected, the party responsible assumed the loss.  For                  
          instance, if the supplier delivered defective concrete or did not           
          deliver the concrete to the site in time to lay it within 1 hour            
          of leaving the supplier’s plant, the supplier assumed the loss.             
          However, if petitioner failed to pour properly delivered concrete           
          in time, petitioner assumed the loss.  The governmental entity              
          worked with petitioner and the supplier but ultimately held                 
          petitioner responsible for any failure to meet contractual                  
          obligations.  Petitioner signed for the concrete after the                  
          government’s inspector found it to be acceptable.  The                      
          government’s engineer gave permission to pour the concrete.                 
          Thus, for instance, if permission was given and concrete was                
          poured, and then the concrete was damaged by rain before it                 
          dried, the governmental entity assumed responsibility.  For State           
          projects, the governmental regulation was so strict that                    
          petitioner did not need to guarantee materials; if the State                
          allowed use of the materials, the State assumed responsibility              
          for defects.  For city projects petitioner guaranteed some                  
          materials, but the city would be responsible in some cases, for             
          instance if its engineer had advised petitioner to pour concrete            
          that was later damaged because of rain.  During the 1990’s, 30 to           
          40 percent of petitioner’s work was for the State of Ohio.                  






Page:  Previous  1  2  3  4  5  6  7  8  9  10  11  12  Next

Last modified: May 25, 2011