Vandra Bros. Construction Co., Inc. - Page 5




                                        - 5 -                                         
               Bids were calculated by estimating the cost of each                    
          individual job that was necessary to complete the entire project.           
          The bid price of most of the individual jobs was calculated on a            
          per-unit basis.  For instance, in arriving at a total bid for the           
          reconstruction of a street in the City of South Euclid,                     
          petitioner bid $28 per square yard to install 9-inch reinforced             
          concrete pavement, and $5 per linear foot to install 6-inch                 
          drainage conduit, and separate amounts for numerous other items.            
          The bid price for some individual jobs was calculated on a per-             
          item basis (for instance, $23 per each 9-foot guardrail post) or            
          on a lump-sum basis (for instance, $60,000 for clearing and                 
          grubbing a certain area indicated in the project plan).  The bid            
          calculation also included the estimated number of units or items            
          that the project required.  However, petitioner would bill the              
          customer on the basis of the number of units or items actually              
          used on the project, not the number shown in the bid.   In some             
          cases, petitioner was required by the customer to state                     
          separately the cost of materials (i.e., without labor), and when            
          so required, petitioner did so on a per-unit or per-item basis.             
          Even if two jobs used the same amount of material, the amount of            
          the bid could have differed substantially, due to different cost            
          of labor and equipment.  For instance, to maintain traffic flow,            
          petitioner might be limited in the amount of work it could                  
          complete in one day, thus increasing costs of labor.  Petitioner            






Page:  Previous  1  2  3  4  5  6  7  8  9  10  11  12  Next

Last modified: May 25, 2011