Sec. 11.121. PERMIT REQUIRED. Except as provided in Sections 11.1405, 11.142, 11.1421, 11.1422, and 18.003, no person may appropriate any state water or begin construction of any work designed for the storage, taking, or diversion of water without first obtaining a permit from the commission to make the appropriation.
Amended by Acts 1977, 65th Leg., p. 2207, ch. 870, Sec. 1, eff. Sept. 1, 1977; Acts 1987, 70th Leg., ch. 544, Sec. 1, eff. Aug. 31, 1987; Acts 1995, 74th Leg., ch. 183, Sec. 1, eff. May 23, 1995.
Amended by:
Acts 2015, 84th Leg., R.S., Ch. 756 (H.B. 2031), Sec. 8, eff. June 17, 2015.
Acts 2015, 84th Leg., R.S., Ch. 829 (H.B. 4097), Sec. 3, eff. June 17, 2015.
Section: Previous 11.090 11.091 11.092 11.093 11.094 11.096 11.097 11.121 11.122 11.123 11.124 11.125 11.126 11.127 11.1271 NextLast modified: September 28, 2016