Sec. 11.126. COMMISSION REQUIREMENTS. (a) If the proposed taking or diversion of water for irrigation exceeds nine cubic feet per second, the executive director may require additional information as prescribed by this section.
(b) The executive director may require a continuous longitudinal profile, cross sections of the proposed channel, and the detail plans of any proposed structure, on any scales and with any definition the executive director considers necessary or expedient.
(c) If the application proposes construction of a dam greater than six feet in height either for diversion or storage, the executive director may also require filing a copy of all plans and specifications and a copy of the engineer's field notes of any survey of the lake or reservoir. No work on the project shall proceed until approval of the plans is obtained from the executive director.
(d) If the applicant is a corporation, the commission may require filing a certified copy of its articles of incorporation, a statement of the names and addresses of its directors and officers, and a statement of the amount of its authorized capital stock and its paid-up capital stock.
(e) If the applicant is not a corporation, the commission may require filing a sworn statement showing the name and address of each person interested in the appropriation, the extent of his interest, and his financial condition.
Amended by Acts 1977, 65th Leg., p. 2207, ch. 870, Sec. 1, eff. Sept. 1, 1977; Acts 1981, 67th Leg., p. 3155, ch. 828, Sec. 2, eff. June 17, 1981; Acts 1985, 69th Leg., ch. 795, Sec. 1.009, eff. Sept. 1, 1985.
Section: Previous 11.096 11.097 11.121 11.122 11.123 11.124 11.125 11.126 11.127 11.1271 11.1272 11.1273 11.128 11.129 11.130 NextLast modified: September 28, 2016