noted in his dissent in the Court of Appeals, "when the MWRA, acting in the role of purchaser of construction services, acts just like a private contractor would act, and conditions its purchasing upon the very sort of labor agreement that Congress explicitly authorized and expected frequently to find, it does not 'regulate' the workings of the market forces that Congress expected to find; it exemplifies them." 935 F. 2d, at 361.
Because we find that Bid Specification 13.1 is not preempted by the NLRA, it follows that a preliminary injunction against enforcement of this bid specification was improper. We therefore reverse the judgment of the Court of Appeals and remand these cases for further proceedings consistent with this opinion.
It is so ordered.