PUD No. 1 of Jefferson Cty. v. Washington Dept. of Ecology, 511 U.S. 700, 36 (1994)

Page:   Index   Previous  24  25  26  27  28  29  30  31  32  33  34  35  36  37  38  Next

Cite as: 511 U. S. 700 (1994)

Thomas, J., dissenting

therefore binding on FERC. Under the Court's interpretation, then, it appears that the mistake of the State in California v. FERC was not that it had trespassed into territory exclusively reserved to FERC; rather, it simply had not hit upon the proper device—that is, the § 401 certification— through which to achieve its objectives.

Although the Court notes in passing that "[t]he limitations included in the certification become a condition on any federal license," ante, at 708, it does not acknowledge or discuss the shift of power from FERC to the States that is accomplished by its decision. Indeed, the Court merely notes that "any conflict with FERC's authority under the FPA" in this case is "hypothetical" at this stage, ante, at 723, because "FERC has not yet acted on petitioners' license application," ante, at 722. We are assured that "it is quite possible . . . that any FERC license would contain the same conditions as the state § 401 certification." Ibid.

The Court's observations simply miss the point. Even if FERC might have no objection to the stream flow condition established by respondents in this case, such a happy coincidence will likely prove to be the exception, rather than the rule. In issuing licenses, FERC must balance the Nation's power needs together with the need for energy conservation, irrigation, flood control, fish and wildlife protection, and recreation. 16 U. S. C. § 797(e). State environmental agencies, by contrast, need only consider parochial environmental interests. Cf., e. g., Wash. Rev. Code § 90.54.010(2) (1992) (goal of State's water policy is to "insure that waters of the state are protected and fully utilized for the greatest benefit to the people of the state of Washington"). As a result, it is likely that conflicts will arise between a FERC-established stream flow level and a state-imposed level.

Moreover, the Court ignores the fact that its decision nullifies the congressionally mandated process for resolving such state-federal disputes when they develop. Section 10( j)(1) of the FPA, 16 U. S. C. § 803( j)(1), which was added as part

735