- 24 - construction of both these sewer system improvements would be $820,000. In light of the conflicting evidence presented regarding this factor, we conclude that a prudent investor would consider the uncertainty of this expense and include the potential cost of extending and upgrading the sewer system into any valuation of the Property. Therefore, we determine that $820,000 must be allocated to the construction of the sewer system for the Property. B. Road Costs Mr. Dallamora presented the most persuasive evidence on road costs. In his valuation, Mr. Dallamora contacted two local contractors, James E. Hanscom16 and Paul J. Fantoni,17 and requested bids on the anticipated road construction costs. Messrs. Hanscom and Fantoni have extensive experience in the construction of roadways in the area. Based upon the bids received from these contractors, Mr. Dallamora estimated that the 16Mr. Hanscom was the director of Public Works for the town of Framingham from 1980 to 1990 and has over 30 years of roadway and site construction experience. 17Mr. Fantoni was the owner of Fantoni Co., a construction company specializing in the construction of underground utilities and bridge building for over 25 years. Mr. Fantoni holds a bachelor of science degree in civil engineering.Page: Previous 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Next
Last modified: May 25, 2011