Allen M. Glick - Page 25

                                       - 25 -                                         
          cost to build the roads in the subdivision would total                      
          $2,123,788.18                                                               
               Mr. Dallamora's road construction expense also included                
          $150,000 for the removal of ledge, an expense item separately               
          stated in Mr. Avery's report.19  Relying upon Mr. Flint's analysis          
          of the composition of the soil on the Property, Mr. Avery                   
          estimated that a separate expense of $370,000 should have been              
          allocated for the removal of ledge.20  We find Mr. Avery's                  
          estimate concerning this additional construction cost persuasive;           
          thus, Mr. Dallamora's estimate for ledge removal must be                    
          increased to reflect this expense properly.  Based upon all the             
          evidence presented, we conclude that the cost to build the roads            
          on the Property, including the cost of removing ledge, would                
          total $2,350,000.21                                                         

               18Mr. Handverger estimated that road construction would cost           
          $2,200,000.  Similarly, Mr. Segel estimated that the expense                
          would total $2,140,000.                                                     
               19Mr. Avery stated that "Ledge is the 'enemy' of a site                
          developer as it adds to development cost and makes road and                 
          building placement more challenging."                                       
               20Mr. Avery's road construction estimate without the ledge             
          removal expense was $2,569,842.                                             
               21We calculate the road cost as follows:                               
                    Mr. Dallamora's estimate ($2,123,788), plus an                    
                    additional amount for ledge removal ($370,000 - 150,000           
                    = 220,000) = 2,343,788 or $2,350,000.                             
               We further determine that this amount would be incurred in             
          two phases, 80 percent in the first phase and the remaining 20              
                                                             (continued...)           