- 7 -
Contractor hereunder and under California law,
including all laws related to latent defects or fraud.
If Contractor reasonably deems it more expedient to
correct any of the Work covered by warranty itself
because of any delay by Subcontractor, a "backcharge"
may be made pursuant to Paragraph 23 below. This
provision shall be binding upon the successors and
assigns of Subcontractor and shall benefit the
successors and assigns of the Contractor; including
purchasers of residences within the Project.
* * * * * * *
Exhibit A, Specific Scope of Work, of the contract provided
the following:
1. General
a. Subcontractor is responsible for all
materials until final installation and
acceptance by CONTRACTOR. Any loss due to
theft or breakage prior to acceptance by
CONTRACTOR shall be replaced by SUBCONTRACTOR
at no additional charge to CONTRACTOR.
b. SUBCONTRACTOR agrees herein that any labor,
materials, and/or workmanship that does not
comply to the CONTRACTOR'S standards shall be
removed and replaced to conform to the
CONTRACTOR'S standards.
c. SUBCONTRACTOR further agrees that the quality
of his workmanship and his materials shall be
in strict accordance with the plans and these
specifications.
* * * * * * *
e. SUBCONTRACTOR shall warranty all concrete foundation
work for two years from acceptance of work by
CONTRACTOR.