- 7 - Contractor hereunder and under California law, including all laws related to latent defects or fraud. If Contractor reasonably deems it more expedient to correct any of the Work covered by warranty itself because of any delay by Subcontractor, a "backcharge" may be made pursuant to Paragraph 23 below. This provision shall be binding upon the successors and assigns of Subcontractor and shall benefit the successors and assigns of the Contractor; including purchasers of residences within the Project. * * * * * * * Exhibit A, Specific Scope of Work, of the contract provided the following: 1. General a. Subcontractor is responsible for all materials until final installation and acceptance by CONTRACTOR. Any loss due to theft or breakage prior to acceptance by CONTRACTOR shall be replaced by SUBCONTRACTOR at no additional charge to CONTRACTOR. b. SUBCONTRACTOR agrees herein that any labor, materials, and/or workmanship that does not comply to the CONTRACTOR'S standards shall be removed and replaced to conform to the CONTRACTOR'S standards. c. SUBCONTRACTOR further agrees that the quality of his workmanship and his materials shall be in strict accordance with the plans and these specifications. * * * * * * * e. SUBCONTRACTOR shall warranty all concrete foundation work for two years from acceptance of work by CONTRACTOR.Page: Previous 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Next
Last modified: May 25, 2011