RACMP Enterprises, Inc. - Page 10




                                       - 10 -                                         
          petitioner.  The type and quality of the concrete was specified             
          by the builder's plans.  When the concrete arrived at the                   
          developer's building site, either petitioner or a quality control           
          technician in the employ of the developer could reject the batch.           
          However, if petitioner was willing to accept the batch, but the             
          quality control technician determined that the batch should be              
          rejected, the batch would be rejected.  The quality control                 
          technician took a sample of the concrete batch during the pour              
          for a "slump test".  The developer had 45 days after taking the             
          sample to reject the concrete if it failed the test.                        
          D.   Billing and Payment                                                    
               After the sand and drain rock had been spread, the hardware            
          items installed, and the concrete poured and finished, petitioner           
          received an invoice for the cost of the materials and a lien                
          release, which also stated the cost of the materials, from each             
          of the materials suppliers.  At the end of the month, petitioner            
          submitted the suppliers’ lien releases and a single invoice for             
          the cost of the completed work to the developer for payment.  The           
          invoice did not itemize the costs of the labor and material or              
          the amount of the profit.                                                   
               The developer paid for the construction work in a two-part             
          process.  First, the developer issued a joint check made payable            
          to petitioner and each supplier for the cost of the materials as            
          stated on each suppliers’ lien release and invoice.  Petitioner             






Page:  Previous  1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  18  19  20  Next

Last modified: May 25, 2011