- 110 -                                                  
                  •     18,095      feet of conduit installation                                        
                  •     1,640       seismic hangers and supports                                        
                  •     100         feet cable tray                                                     
                  •     88,810      feet of cable (reroute)                                             
                  •     11,410      cable terminations and determinations                               
                  •     4,500       feet of raceway (conduit) protection                                
                  •     650         Supports to protect                                                 
                  •     75          Pull and terminal boxes to protect                                  
                  •     300         Pieces of equipment to install (valves,                             
                                    valve actuators, switches, local control                            
                                    stations, instruments, etc.)                                        
            Attachment 2 contains a raceway-by-raceway list of the additional                           
            work needed at Turkey Point Units 3 and 4.  Unlike attachment 1,                            
            attachment 2 does not contain the same specific itemized and                                
            quantified descriptions of the raceway property.  We find that                              
            Letter No. L-85-385 readily identifies FPL’s raceway protection                             
            property at Turkey Point Unit 4 because attachment 1 lists the                              
            components of the raceway protection system that FPL needed to                              
            install.102  However, we find that this letter fails to readily                             
            identify the specifications and amount of the Turkey Point Unit 3                           
            raceway protection property.                                                                
                  102 We address this issue to complete our analysis of the                             
            supply or service contract transitional rule.  However, the                                 
            property does not qualify for an ITC because we have held that                              
            the tariff is not a supply or service contract for purposes of                              
            TRA sec. 204(a)(3), and we have held that the tariff does not                               
            incorporate the “related documents”.                                                        