FPL Group, Inc. & Subsidiaries - Page 170

                                       - 55 -                                         
               air.  Additional air stations are needed to be                         
               installed in order to provide the equipment with the                   
               necessary instrument air.  Two new additional air                      
               compressors will be installed, and the air dryer will                  
               be replaced.                                                           
                    The present air compressors are operating                         
               continuously indicating insufficient air capacity.  The                
               system suffers from a lack of adequate pressure for the                
               main steam isolation valves * * *.  The existing dryer                 
               is not properly drying air at the present system flow                  
               rates.                                                                 
          ER No. 9009 estimated that the upgrade would be completed by                
          November 30, 1986.  In late 1985, the amount authorized was                 
          increased to $692,000.  In late 1988/early 1989, the ER was                 
          increased to $1,765,000 “due to schedule duration increase and a            
          growth in scope.”  The duration increase was due to “rescheduling           
          of Engineering and a Plant Operations requirement that some work            
          be accomplished during a plant outage.”  According to a report of           
          construction action, the construction began on October 26, 1985.            
          According to another report of construction action, construction            
          stopped to await a construction package needed to complete the              
          work, and the work was to resume during the summer of 1987.                 
               ER No. 9303, processed on February 26, 1986, authorized                
          $692,000 to upgrade the instrument air system on St. Lucie Unit             
          2.  ER No. 9303 essentially listed the same need for the upgrade            
          as described in ER No. 9009.  In late 1988/early 1989, FPL                  
          increased the amount authorized to $1,464,000 because of growth             
          in the scope of the project.  According to a report of                      
          construction action, construction started on the instrument air             





Page:  Previous  45  46  47  48  49  50  51  52  53  54  55  56  57  58  59  60  61  62  63  64  Next

Last modified: May 25, 2011