- 38 - 1984/early 1985, FPL revised this BI to increase the overall budgeted amount to $35 million. ER No. 7172, referencing BI No. 543, was processed in 1984 and approved $10,675,000 to design, fabricate, and install a control room specific simulator for the St. Lucie power plant. This ER was revised in late 1988/early 1989 to increase the amount approved to $13,150,000 and revised again in 1991 to increase the amount approved to $14,520,000. ER No. 8223, referencing BI No. 543, was processed in 1985, and authorized $375,000 to provide detailed design and engineering necessary to construct the training facility at the St. Lucie nuclear power plant. FPL revised this ER in 1986 to increase the amount approved to $5.5 million, and again in 1988 to increase the amount approved to $7,050,000. ER No. 7173, referencing BI No. 543 and approved in 1984, authorized $10,780,000 to design, fabricate, and install a control room specific simulator for Turkey Point. This ER was revised in late 1988/early 1989 to increase the amount approved to $11,550,000. A 1987 BI No. 103, approved in 1986, budgeted $2,437,000 to “provide the capital additions necessary to equip the Training/Simulator [at the St. Lucie nuclear power plant] with state of the art tooling, mockups, and equipment.” ER No. 1817, which references BI No. 103 and was approved in early 1987, authorized $330,000 to purchase mockup equipment and plantPage: Previous 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 Next
Last modified: May 25, 2011