FPL Group, Inc. & Subsidiaries - Page 185

                                                - 70 -                                                  
            terminal in the Ranch substation.75  FPL revised this budget item                           
            in 1985 to decrease this project’s budget to $7 million.                                    
                  A 1983 BI No. 274 budgeted $28.4 million as a conceptual                              
            estimate to construct a new 500-240-kV transmission substation,                             
            the Corbett substation, consisting of four 500 MVA                                          
            autotransformers, one 500-kV line terminal and four 240-kV line                             
            terminals.  According to the budget item, the work was to begin                             
            in November 1985 and was to be completed in May 1987.                                       
                  A 1985 BI No. 272 budgeted $24.2 million as a conceptual                              
            estimate to construct approximately 33 miles of 500-kV                                      
            transmission line between the Corbett substation and the Martin                             
            plant.76  It also states FPL’s plan to construct a 500-kV                                   
            terminal at the Martin plant switchyard.77  The budget item                                 
            scheduled work to commence in May 1986 and to be completed in May                           
            1987.  ER No. 1248, which refers to BI No. 272 and was processed                            


                  75 Thomas Sanders, an engineer employed by FPL, testified:                            
                        This is the construction of 13 miles of new 230 KV                              
                  line.  There are two miles of 230 KV line.  Between the                               
                  two constructions, they basically integrate the 500 KV                                
                  Corbett substation with the existing 230 KV system                                    
                  that’s in the area.  There is also a reconductoring of                                
                  the 230 KV line from Cedar to Ranch and the two 240 KV                                
                  terminals for the Corbett lines and the upgrade of the                                
                  Cedar and the ranch terminal.                                                         
                  76 BI No. 272 was originally authorized in 1983 for $23                               
            million.                                                                                    
                  77 Mr. Sanders testified that, according to this budget                               
            item, this work was needed “to reliably transfer contracted                                 
            foreign power purchases from the Southern [Companies].”                                     




Page:  Previous  60  61  62  63  64  65  66  67  68  69  70  71  72  73  74  75  76  77  78  79  Next

Last modified: May 25, 2011