- 72 - A 1987 BI No. 304, entitled “Transmission Plant-- Systemwide--Miscellaneous--1987”, approved in 1986, budgeted $9.8 million for transmission lines, substations, relay projects, and miscellaneous projects. ER No. 3276, approved in late 1987/early 1988, authorized the expenditure of $738,140 to replace five 230- kV transmission breakers at the St. Lucie plant. On the basis of a study by the system planning department, the ER states that the then-existing breakers would become overstressed because of the 500-kV transmission expansion. A 1989 BI No. 267, entitled “Transmission Plant--Systemwide--Miscellaneous--1989”, approved in 1988, budgeted $23,456,000 to, inter alia, upgrade and replace various transmission lines. ER No. 5334, approved in late 1988/early 1989, authorized the expenditure of $1,192,967 to install one 500-kV bus tie breaker at the Poinsett substation. ER No. 1776, approved in 1987, authorized the expenditure of $3,401,908 to install a 500-kV 2 breaker terminal.80 A 1988 BI No. 264, approved on October 15, 1987, entitled “Transmission Plant Systemwide Miscellaneous--1988”, budgeted $12,045,000 to, inter alia, install high voltage switched capacitor banks at three locations. ER No. 3216, approved in late 1987/early 1988, authorized the expenditure of $1,257,310 to add two 230-kV MVAR 80 Mr. Sanders testified that this expenditure was “an integral part of the 500 KV transmission system that we built.”Page: Previous 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 Next
Last modified: May 25, 2011