FPL Group, Inc. & Subsidiaries - Page 193

                                                - 78 -                                                  
            the Trace substation.  The BI stated that “Extensive development                            
            is presently occurring in the Southwest Broward County area”.                               
            Apparently, FPL anticipated that one development project in this                            
            area would have an ultimate peak demand of 270 MVA.  New                                    
            substations were anticipated to be built, and FPL proposed to                               
            construct a fourth Andytown-Lauderdale plant 230-kV line to serve                           
            the new substations.85                                                                      
                  ER No. 1333, which referenced BI No. 246 and was approved in                          
            late 1986, authorized the expenditure of $2,502,710 to construct                            
            approximately 9.5 miles of single pole concrete 230-kV                                      
            transmission line from the Andytown substation to the Trace                                 
            substation.  ER No. 1645, which referenced BI No. 246 and was                               
            processed in late 1986/early 1987, authorized the expenditure of                            
            $962,036 to install equipment at the Andytown substation.  ER No.                           
            1676, which references BI No. 246, authorized the expenditure of                            
            $152,090 to install equipment at the Andytown substation.                                   
                  A 1986 BI No. 253, approved in late 1985, budgeted $1.1                               
            million to construct approximately 3.5 miles of single circuit,                             
            single pole concrete 230-kV line to serve the Trace substation.                             
            The BI states that the project was initially authorized in 1984,                            
            and that the project was completed in May 1985.  The reason for                             
            the BI was “to construct Trace Substation by the summer of 1985                             


                  85 Mr. Sanders testified that “This line was constructed to                           
            serve the load growth in western Broward County.”                                           




Page:  Previous  68  69  70  71  72  73  74  75  76  77  78  79  80  81  82  83  84  85  86  87  Next

Last modified: May 25, 2011