FPL Group, Inc. & Subsidiaries - Page 190

                                                - 75 -                                                  
            Florida.83  FPL had a reliability problem because a single                                  
            transmission line fed several substations in the area.  As a                                
            result, if the transmission line lost service at one end, all of                            
            the substations would experience an outage.  FPL planned to break                           
            that line into two segments, including the new Midway-Jensen-                               
            Crane line.  To reliably serve the load in that area, the plan                              
            also called for additional distribution substations to the west.                            
                  A 1982 BI No. 244, approved in late 1981, budgeted $1.5                               
            million to:  (1) Acquire 16 miles of 15-foot-wide right-of-way                              
            from Jensen substation to Midway substation; (2) acquire a 10-                              
            acre substation site for a distribution/switching station from                              
            Turnpike substation; and (3) acquire 7.5 miles of 15-foot-wide                              
            right-of-way from the Turnpike substation to the Crane                                      
            substation.  According to the BI, the work was to be started in                             
            January 1982 and was to be completed in December 1985.  FPL                                 
            revised BI No. 244 in late 1982 to increase the amount authorized                           
            by $200,000 to acquire an additional 1.5 acres at the Jensen                                
            substation for its expansion.  In early 1982, ER No. 5058, which                            
            references BI No. 244, authorized the expenditure of $200,000 to                            
            purchase approximately 10 acres of land as a site for the                                   
            purposed Turnpike substation.                                                               



                  83 Mr. Sanders testified that the Midway-Turnpike-Jensen                              
            transmission line system operated as an integrated unit, and that                           
            FPL viewed the system as one integrated piece of equipment.                                 




Page:  Previous  65  66  67  68  69  70  71  72  73  74  75  76  77  78  79  80  81  82  83  84  Next

Last modified: May 25, 2011